Leddin West T101 Substation

63 MVA Grid-Connected Capacity - Flexible Project Planning

Power transformer at an electrical substation on a concrete foundation, with high-voltage switchgear, insulators and steel structures for connection to the power grid.

The project was completed in just 3.5 months, from mid-August to the end of November 2025. With a grid-connected capacity of up to 63 MVA, the facility represents another step toward the energy transition.

A unique aspect of the project was the temporary relocation of the underwater components, as the building permit process presented several challenges. Thanks to precise planning and close coordination, however, all components were seamlessly integrated.

With the completion of Leddin West T101, we are taking another step forward in the development of modern energy infrastructure and look forward to our upcoming projects with enthusiasm.

Your Contact Person

Talk to us about your 110-kV project

The sooner we're involved, the easier it will be to plan your grid connection. Let's go over your project together.