A 110/30 kV substation is currently being built on the green meadow near Kittlitz in Brandenburg. WKN AG commissioned WT Energiesysteme with the turnkey construction of the substation, including a 20/25 MVA power transformer. The transformer station Bischdorf Süd III will enable the supply of wind energy with a capacity of 25 MVA to the public grid.
Location:
03222 Kittlitz (Brandenburg)
Voltage level:
110/30 kV
Power transformers:
20/25 MVA ONAF
Client:
WKN AG
Scheduled startup:
01/18/2019
Image: google maps