transformer station Prutz 110 kV field extension line GKI 1 and GKI 2

Umspannwerk Prutz in Österreich

WT Energiesysteme GmbH has been awarded the contract to extend the 220/110/25 (30) kV transformer station Prutz with two 110kV power lines GKI 1 and GKI 2. The following services are required:

     

  • Construction of the Small Foundations
  •  

  • Integration into the existing earthing network
  •  

  • Installation, stranding and wiring of the provided devices
  •  

  • Field control cabinet including foundation
  •  

  • Cabling of the secondary technology in the existing cable duct to the operating building
  •  

  • New protective cabinet for the line protection of the two branches
  •  

  • Removing the conventional control in the control room with control / acknowledgment switches
  •  

  • Extension of the existing telecontrol system
  •  

  • Implementation planning of secondary technology in Ruplan
  •  

  • Function test and commissioning

Client:
TIWAG – Tiroler Wasserkraft AG

Location:
A-6522 Prutz (Tyrol)

Period:
14.05.2018 to 15.02.2019